Renovation
of the West Auditorium at Yosemite National Park
Thisproject consisted of the interior demolition
of the existing West Auditorium. The new renovation consisted
of new storefronts, stage, seating platform, architectural wood
trim throughout, acoustical ceilings and walls, new HVAC system,
specialty lighting and sound system. This project required that
it be completed during the winter months. Snow, cold weather and
strong winds made this project complex for accessibility and material
delivery. We had had only five months to complete this project
-coordinating long lead items in such a short time required a
tight schedule and strong follow up. Coordination of various trades
in such a small area created various Safety Hazards. JI Garcia
Construction meet with Subcontractors weekly to plan a two-week
look-ahead schedule to avoid safety hazards and conflicts. Architectural
features included extensive specialty carpentry that needed to
be stained. This lumber required a constant heat temperature of
at least 65 degrees; in order to maintain this temperature JIG
set up a temporary heating system until the Heating Coils were
installed in the new HVAC system. The auditorium was ready for
the grand opening of the"Spirit of Yosemite" movie as
scheduled.
|