This
project consists of the design and construction of a new, approximately
12,271 SF, Enlisted Barracks Addition to Building 836 to bring
up a total of approximately 22,933 SF to house a total of 44 E5
and E6 personnel at the Presidio of Monterey Phase III for the
U.S. Army Corps of Engineers, Sacramento District. The building
will be constructed using cold-formed metal stud bearing wall
framing, exterior plaster systems, wood truss and concrete tile
roof.
This project includes the additions of
two 3-story room cluster towers on each side of the existing building
including bedrooms, lounges, fire protection (detection/alarm
system), utilities, and communications. Electrical, mechanical
and plumbing upgrades are also required. Anti-terrorism/force
protection (AT/FP) measures will also be incorporated in the design
of the structure.
|